|
Asphalt innovation
New technology makes asphalt more
competitive, longer lasting
By Angelle Bergeron
In Louisiana, researchers relentlessly concoct asphalt mixes
suited to the state's unique environmental and usage demands.
Technology, materials and new application procedures and equipment
allow asphalt to be tailor-made for virtually every sort of
application.
"I've been studying asphalt since 1987, and over the
years technology has advanced so much that it allows us to
apply tools for the characterization of asphalt mixtures,"
said Dr. Louay Mohammad, director of the Engineering, Materials,
Characterization Research Facility at the Louisiana Transportation
Research Center.
"That will allow us to understand the load and viscosity
over a range of temperatures and densification properties
of a sample while it is compacting. If we can engineer the
right material, we can prevent failure."
This month, LTRC kicked off a new study funded by the National
Cooperative Highway Research Program. The study, called Optimization
of Tack Coat for HMA Placement, will determine the optimum
application methods, equipment type, calibration procedures,
application rates and asphalt-binder materials for the various
uses of tack coats.
"We want to come up with a best material that will allow
the layers (of asphalt applications) to act as one monolithic
system," Mohammad said. "The idea is to improve pavement
performance."
Density is usually difficult to achieve with one layer, but
finding the appropriate glue to hold the layers together is
also a challenge. Cracking and slippage of whole layers are
typical problems that LTRC is hoping to remedy through this
study.
Huey Stockstill, a Picayune, Miss., contractor, recently
applied a test section of trackless tack coat on La. Hwy.
3235.
"It's a polymer modified tack coat that sets up in about
10 minutes and doesn't track up," said Sam Cooper, senior
asphalt research engineer at LTRC. The test site marked the
first time LTRC used the material, and evaluations were scheduled
to be complete by the beginning of this month.
The cure time varies according to the application levels
and temperature, but the section actually cured in about nine
minutes, said Leo LeBourgeois, project manager for Huey Stockstill.
"They claim you can shoot it days ahead of time and
the weather won't hurt it," LeBourgeois said. "We
didn't have any rain, so we didn't have a chance to test that,
but we did leave it overnight."
The tack test section represented only a small area of the
5-mi. overlay project that ran from Golden Meadow to La. Hwy.
3162 in Lafourche Parish. The $4.1 million contract required
application of a very fine mix of Level 1 Superpave, LeBourgeois
said.
"They were concerned about the subgrade breaking down,
not being able to take the compactive effort, and this mix
doesn't require too much compactive effort to get the proper
density on the asphalt," he added.
Because of the fineness of the aggregate, the contractor
had difficulty obtaining the desired mix.
"We had to redo mix designs >> several times because
we weren't able to get the amount of voids in the aggregate
that we needed," LeBourgeois said. "We did do some
test patterns on the existing asphalt with the rollers to
decide what compactive efforts could go into the subgrade,
and LTRC came out and tested before we even started laying
down the asphalt."
Gilchrist Construction Co. of Alexandria is working on an
$18.7 million project on U.S. Highway 171 from Noble to Converse
that will also feature Level 1 Superpave.
"We have a good mix design so it shouldn't be a problem,"
said >> Raymond Boniol, company engineer for Gilchrist.
"We will be doing the hot mix ourselves and will probably
start laying asphalt in late July or early August. We've done
Superpave before, and our equipment is in good shape for it."
L&A Contracting of Hattiesburg, Miss., has a $15 million
four-laning contract for a section of U.S. Highway 165 from
Pollock to LA 524 that is primarily Level 1 Superpave.
"The town section (through Pollock) is concrete paving,
but the rural areas are all asphalt," said Lawrence Salard,
project superintendent. The town portion represents only .25-mi.
of the 3-mi. job, which also includes construction of five
new bridges and removal of three existing bridges.
"U.S. 165 has been a pinpoint area for DOTD and there
is construction south and north of us," Salard added.
D&J Construction of West Monroe recently completed a
repair and overlay project for DOTD on a section of Interstate
20 using an open-graded friction course that is another test
project for LTRC. D&J bid on the Britton Road to Vancil
overpass job in October and won the A+B (base bid plus calendar
days), $1.8 million, 60-day contract.
The contractor began work in mid-April cleaning the section,
sealing cracks and applying a 1-in. overlay of open-graded
friction course.
"We were overlaying existing asphalt because it's wheel-rutted
and the aggregates have become polished, causing a hazard
when motorists apply brakes," said Jerry White, vice
president of operations for D&J. "They were having
problems with hydroplaning in this particular section."
In 1984, DOTD placed a moratorium on open-graded friction
course because of moisture-related problems that resulted
in raveling, LTRC's Cooper said.
"The mix really hasn't changed that much, but one of
the aggregates gave us a problem in the '80s," he added.
"Now we've got the asphalt contents back up to where
they were in the late '70s, and with the addition of polymers
and fibers we don't have the problems they did back then."
Although chosen for durability and reduction of hydroplaning,
the open-graded friction course has the added benefit of providing
noise reduction.
"It's at least a 50 percent reduction in noise already,"
White said. "We have asphalt on one end of the site and
concrete on the other, and you can really tell the difference
when those cars come off the concrete on the other end. And
there is virtually no overspray with those big 18-wheelers
because the water runs through the OGFC and out the side."
Reduction of splash and spray are the primary benefits of
OGFC, but the asphalt mix is limited because it is thin, Mohammad
said.
"It can only work if it is put on a good layer to start
with," he added..
D&J's White said OGFC is a good product, but it requires
a special self-priming layer for application.
"It carries its own tack coat on the paver that is applied
before the asphalt," he added. "I had to hire a
four-man crew from E.J. Breneman out of Pennsylvania to come
in and lay it."
White, who oversaw an ultrathin job last year using another
tack coat, said D&J would buy the special paver if the
state would let enough work to justify the purchase.
Barriere Construction Co. of New Orleans had to make some
adjustments to its Boutte plant to produce a stone-matrix
asphalt mix it is applying on Interstate 10 in Metairie.
The SMA placement is the first under the new DOTD specifications
but will probably become the norm for interstate jobs because
the mix is durable and long-lasting, said Don Weathers, executive
director of the Louisiana Asphalt and Pavement Association.
"We've done SMAs in the past, but we didn't have all
the goodies we do now, the polymers and fibers," Weathers
added. "It's a lot more expensive, but holds up better
under heavy loading and will last. That's why they're putting
it down on I-10."
Barriere is placing a 2-in. single-lift overlay of the SMA,
which is a stone-on-stone contact mix with high asphalt cement
content and a great deal of fibers and dust to control the
drain-down of the liquid in the mix.
"Ordinarily, the liquid would drain down to the bottom
and the asphalt would not last as long. It would come apart,"
said John Victory, quality control manager for Barriere. "The
fibers and dust make it like a chewing gum consistency where
it won't drain down."
DOTD will now require the new mix for all projects with 35,000
average daily traffic or greater, said Chris Abadie, materials
research administrator for LTRC.
"This is the premium mix, the mix with the longest durability
and fatigue life, so you want this on the surface of all your
high-traffic areas," Abadie said. "It's the best
mix we have but it's also the most expensive, so we have to
make a decision where we want to put it."
The 15-year life expectancy of SMA is still half of concrete,
but it is less expensive and may be applied in a thin layer,
he added.
The consistency of the mix and nighttime application require
the contractor to apply it quickly. The contractor established
rolling patterns to meet density requirements and closely
monitored travel times from the plant to the site.
Useful Source:
For more about research initiatives at LTRC, go to: http://www.ltrc.lsu.edu/
|