|
New brothers
Iberville, Bienville buildings
to complete Baton Rouge foursome
By Angelle Bergeron
Explorer brothers Iberville and Bienville opened the gateway
from the Gulf of Mexico to the Mississippi River, and two
government buildings bearing their names will soon grace the
entry to Baton Rouge's new Capitol Park.
The buildings under construction look like brothers in many
ways. Both are nine stories, mimic the art deco design of
the Louisiana Capitol and feature exterior finishes of precast
concrete panels, glass curtain walls, aluminum wall panels
and third-floor roof terraces facing the Capitol.
The buildings will complete a foursome of structures (preceded
by the LaSalle and Galvez buildings) in Capitol Park that
face the Louisiana Capitol. All of the buildings are owned
by the state and will house government agencies.
The Iberville building is scheduled for completion in April
and the Bienville building in May.
Ratcliff Construction Co. of Alexandria is working on the
Bienville Building and Milton J. Womack of Baton Rouge is
contractor for the adjacent Iberville Building.
The two contractors are working in tight spaces with limited
laydown areas and fast-paced schedules, yet their projects
differ in several ways.
The nine-story Iberville, which will house the Department
of Social Services, is slightly larger than its counterpart
and will boast a basement. Its design also features two shear
walls at the core of the building, whereas the Bienville is
structural steel and poured-in-place concrete.
Womack was scheduled to begin construction of the $28.4 million
Iberville building in March 2004, but the contract was extended
for 30 days because of >> demolition delays, said Stephan
Dorsey, project manager.
Holly & Smith Architects of Hammond and consulting engineers
McKee & DeVille of Baton Rouge designed the Iberville.
"By the time we moved in, the only thing that was here
was the basement slab from the old building," Dorsey
said. Womack cored the existing basement and drove about 70
precast concrete piles as foundation, then poured the foundation
slab.
"After we poured the slab, we started pouring the shear
wall," Dorsey added.
As a segment of the shear walls was complete, Womack erected
steel, then the metal decking for the poured-in-place concrete
slab floors.
Most of the concrete was poured at night, so the contractor
was able to stage the work in the street and move out before
disrupting the early morning traffic flow.
"Our supplier, Heck Concrete of Baton Rouge, told us
they were experiencing some problems with the cement supply
last summer, but they didn't slow us down any," Dorsey
said. "We did have some steel price increases about a
year ago. We went to the state to try to help us absorb the
price increases, but it said it wasn't able to."
Fortunately, the subcontractor helped mitigate some of his
costs with the steel mill.
The contractor is erecting the building in east and west
halves, which was the only way it could perform the work on
a site barely larger than the 270,000-sq.-ft. building's footprint.
"When we erected the west half, we used the footprint
of the east half as a storage area," Dorsey said.
He added that the west half of the building is tied into
both shear walls and, as the east half was constructed, it
was tied into the existing portion.
"You plumb up one half and you hope the other half plumbs
up just as good," he said.
The consulting engineer ordered surveys after completion
of the third, sixth and ninth floors to make sure everything
was within acceptable tolerances. "He wanted to check
it periodically instead of waiting too long, but we didn't
have any problem," Dorsey said.
Currently, the contractor has completed erection of most
of the precast concrete and the roof, installed most of the
windows and is about halfway down the building with interior
drywall.
At the $30.5 million Bienville building site, demolition
crews had left nothing behind but a few slabs and pile caps
when Ratcliff mobilized for construction in April 2004.
"We had one big slab, about 3 ft. thick, that covered
the old parking garage area," said Jeff Robichaux, superintendent.
"We busted through the concrete, backfilled with dirt
and then drove the pilings in those holes, 95 ft. into the
ground."
More than 100 of the building's 302 pilings were driven in
that one area, Robichaux said.
"That's something we knew we were going to have to do,
but we did find a couple slabs that we didn't know were there,"
he added. "Some areas that were supposed to be removed
by the demolition contractor weren't removed for some reason
or another."
Architects for the Bienville building are Washer, Hill and
Lipscomb Architects of Baton Rouge and Eskew, Dumez and Ripple
of New Orleans. The 263,605-sq.-ft. building, which will house
the Department of Health and Hospitals, is made of structural
steel with reinforced concrete grade beams and concrete floors.
Storing the precast components posed a problem on a project
where, like the Iberville, the footprint of the building almost
completely filled the jobsite.
"One of the challenges is to get the materials onsite
and store them when you need them, especially when the state's
policy is not to pay for offsite materials,"
Robichaux said. "Our subcontractor, Arkansas Precast
(of Jacksonville, Ark.), can't afford to build several million
dollars of precast and not be paid for it, so it has to be
made as we go."
The Bienville is supported by steel X-bracing that runs through
the center of the building from bottom to top.
"We placed several thousand yards of concrete in the
ground to support this structure," Robichaux said. "In
the ground is a massive concrete weight that is 15 ft. tall
and 9 ft. wide. There are probably 700 or 800 yds. of concrete
in one big footing that the X-brace sits on."
Before pouring the concrete, Ratcliff excavated 15 to 20
ft. below finished floor grade.
"The hole was probably 70 by 70 ft. sq.," Robichaux
said. "It was huge, but we had to have enough room to
get the steel tied and the concrete poured."
The contractor poured several hundred yards of 4,000 psi
concrete at a time.
"We probably put several thousand yards of concrete
into the ground," Robichaux added.
Ratcliff is currently installing sheet rock and exterior
window and panel systems. DHN Corp. of Memphis is manufacturing
and installing all of the windows and metal panels. Joe Banks
Drywall of Mangham is installing the sheetrock.
Lisa Smeltzer, project manager for the state, said coordination
of the numerous subcontractors at the two state building sites
has been important because there are so many of them.
But she added, "We're on schedule and I have no complaints."
<<
Useful Source:
For a list of projects completed in downtown Baton Rouge
since 1997, go to: http://brgov.com/dept/ddd/projects1987.htm
|