|
Monkey business
Primate research units, 'primadomes'
added during New Iberia project
By Karla Wall
Construction will be completed in early 2006 on the $8.3
million expansion of the New Iberia Research Center that houses
primate research programs.
The project, headed by M.D. Descant Inc. of Bunkie, will
add approximately 34,000 sq. ft. to the facility, including
two primate research/housing units and five "primadomes,"
or primate housing units.
The University of Louisiana at Lafayette owns the 100-acre
center, located on a former naval base just outside New Iberia.
Construction began in July 2004.
The five primadomes, three measuring 2,500 sq. ft. and two
1,500 sq. ft., will be arranged in a semicircular pattern
and are open to the air and joined by breezeways or walkways.
The two research buildings - one housing a chimpanzee unit
and the other a rhesus monkey unit - include lab facilities,
anterooms, locker and cleanup areas for employees and up to
16 large cages for the animals.
Project manager Trent Descant said foundation work for the
buildings consisted of 30 25-ft.-deep poured-in-place concrete
pile shafts.
Electrical work began last fall, before actual construction
started, said Eddie Bienvenue of E.P. Breaux Electrical of
New Iberia. All primary services to the area were rerouted,
trenched under the foundation in 3- to 4-ft. trenches during
a six-hour outage, Bienvenue said.
The outage was carefully coordinated to avoid disruption
of activities in the existing facilities.
"We couldn't just take any outage we wanted," Bienvenue
said. "The owner has a pretty tight schedule."
He added that compaction for the underground electrical work
meant dealing with conditions that were either too dry or
too wet for most of the project's duration.
The existing 200 ft. of 400-mcm cable feed was replaced with
600-mcm cable to increase conductive capacity. A new 1,000-kw
pad-mounted transformer replaced the existing 750-kw unit
in the primadome area and a new transformer was pole-mounted
for the research and housing units, Beinvenue said.
The exterior walls of each building are formed of brick veneer,
with about 200,000 bricks used in the project.
"This has been a large masonry job," Descant said.
Lewis Masonry of Bunkie performed masonry work.
Interior walls of the buildings were formed with 8- by 8-
by 16-in. concrete blocks, and all cells were poured with
solid concrete. Roughly 3,000 cu. yds. of concrete were used
in the total project, Descant said. A main concern with the
exterior concrete work was moisture control, and all blocks
were dried and cured correctly in the South Louisiana humidity.
Door facings and frames on each of the two research facilities
will be of a polymer/fiberglass material, Descant added.
Design of the research buildings was done under restrictions
and requirements for biohazard safety levels two and three,
said project architect John Robbins of Bate/Robbins Architects
in New Iberia.
Requirements for exhaust, ventilation, temperature control
and airflow had to be incorportated into the design.
About 35,000 sq. ft. of polymer flooring is being used on
the primadomes and the research buildings. It is manufactured
and installed by Stonhard Inc. of Shreveport.
The floor will be seamless and trowel-installed with an integral-coat
base. Trowel installation allows for a thicker, more durable
floor, said Dave Reich, Shreveport territory manager for Stonhard.
Installation in all the buildings should take about five weeks.
The Stonclad flooring was chosen because "it'll hold
up to the chimps," Reich added.
The flooring consists of several layers, including a substrate,
a primer coating, the troweled Stonclad material and a protective
coating. The flooring is used extensively for veterinary hospitals
and animal holding facilities.
Several major electrical systems are being installed for
the project, Bienvenue said. E.P. Breaux installed housing
and contacts for security access systems, temperature control
systems, safety latches and locking mechanisms on doors.
Temperature control is critical in this project, Bienvenue
said.
"If the temperature fluctuates, it can affect the baseline
(of experiments and research)," he added.
Two chillers in the power plant behind the main research
building will supply the rhesus and chimpanzee research buildings.
The primadomes each have a self-contained air-conditioning
unit and control system, Beinvenue said. Switches at each
pod will allow for individual control.
He added that the main gear center for the system will be
routed underground to each pod or building. About 1,500 ft.
of cable will be used in the research facilities and about
5,000 ft. in the pod areas.
Interior conduit is fed overhead through a combination of
rigid or electromagnetic conduit. Two main pipe racks will
be mounted on the steel superstructure and will be placed
along the corridors in the research facilities. Most of the
feeds will be dedicated and will be installed in conjunction
with the interior walls.
"They'll be assembled in the concrete blocks,"
Bienvenue said.
A 1,040-kw natural-gas-powered backup generator, weighing
around 37,000 lbs., was installed behind the main research
facility using a 60-ton crane.
"Backup power is crucial," Bienvenue said. "The
owner has to be able to maintain ventilation, lighting and
equipment, and temperature control even when the primary power
is out."
Descant said the project is spread out, making the coordination
of deliveries difficult.
"We have to make sure that tools, equipment and materials
are delivered to the correct portion of the site," he
added.
Weather conditions have also been a concern. Rain delays
affected the underground work for the electrical portion of
the project.
Useful Source:
For more information and background about the New Iberia
Research Center, go to: http://nirc.louisiana.edu/
|