| Precast Puzzle
Port of New Orleans prepares new home for Carnival Conquest By
Angelle Bergeron The Port of New Orleans is preparing for the Carnival Conquest,
a 3,700-passenger, 1,200-crew cruise ship that will make the Crescent City its
home port.
Broadmoor LLC is working diligently to ensure the ship will
be greeted in December with a new four-story parking garage atop a two-story cruise
terminal that is the first of its kind in the area.
|
Constructing the $35.5 million, six-story, precast Erato Street
Cruise Terminal has been no small feat on a site that is slightly larger than
the building's footprint, perched on the crest of an embankment overlooking the
Mississippi River and in the shadow of the second span of the Crescent City Connection
bridge.
Before the first pile was driven by subcontractor Boh Bros. Construction
Co. of New Orleans, the Port of New Orleans laid down the law about not interfering
with existing cruise passenger traffic.
The toughest part of the job continues
to be coordinating subcontractors, laydown and materials delivery, said Grayson
Bultman, project manager for Broadmoor.
"We are everywhere we can
be right now," Bultman said as crews from Boh Bros. poured a deck beneath
the cavity slab, Broadmoor worked on placing elevated grade beams and Gates Precast
of Houston placed hollow-core planks to form the substructure to the slab on grade.
Crews
are currently hustling to finish work at the south end of the site, while Tindall
Corp. of Biloxi, Miss., is tying together the huge precast elements of the structure
on the north end.
"It's sort of an assembly-line deal with the downstream
end leading the construction," said Kyle Jones, deputy director of port development.
The project broke ground in October when Boh began site utility work and
pile driving. Boh was also responsible for construction of a cavity slab and installation
of a sheet-pile wall, both of which serve as the main-bank stabilization features
of the new structure.
"This facility is right on top of the riverbank
at elevation 20 ft. above sea level, which is a precarious place to be,"
Jones said. "The river in some places is more than a 100 ft. deep and the
city is 5 to 10 ft. below sea level. It's an engineering feat to design this."
When
building close to the river it's necessary to "relieve the driving force
of the tendency of the bank to slough off into the river," said Don Makofsky,
president of Morphy Makofsky Inc., the New Orleans engineering firm charged with
designing the foundation. His firm has designed other structures along the riverfront,
including the Aquarium of the Americas and One River Place Condominiums, but none
quite so unusual.
Jones couldn't recall the port having built any cavity
slabs on any of its properties in the last 15 years.
"In fact, I
don't know if any of our existing facilities have a cavity except for Thalia Street
right next door, which is an 80-year-old wharf," he added.
The Port
of New Orleans, in conjunction with CH2M Hill of Englewood, Colo., the project's
architectural firm, opted for precast construction because of the space restrictions
on the site and the fast-paced construction schedule.
"There's nowhere
to lay anything down," Bultman said. "You can see we're using every
inch of the site for foundation work, so we couldn't support vertical construction
in this space with all of the concrete work we have."
Boh Bros. had
to make adjustments to its pile-driving equipment to work beneath the CCC bridge,
and Tindall will face similar challenges when lifting the upper pieces of precast
into place, Jones said.
Tindall is manufacturing the structural panels,
double Ts, columns and beams. The company has subcontracted Jackson Precast (formerly
Jackson Stone) of Jackson, Miss., to manufacture the architectural panels that
will comprise the decorative, exterior skin and Gates handled the hollow core
planks.
"Tindall will bring in a 400-ton crane and will be putting
up an average of 15-20 pieces per day, so it has to have full access to the site,"
Bultman said. Tindall began erection in May and is on a five-month schedule.
"That
means we need to have all of our foundations complete by the end of July."
Although the precast design costs an estimated 20 percent more than would
a post-tensioned concrete building, it was chosen because of site restrictions
and the fast-approaching December deadline, Jones said.
"We were
willing to let at a premium for a building we could build quicker," he added.
Additional
ships have indicated they would like to port at the terminal and revenue from
the parking garage will be about $12,000 per day, he added.
"It is
vital that we get it up and running by the December completion date," Jones
said.
The precast design offers little tolerance for error with dowels,
anchor bolts and the foundation, Bultman said. And there is little margin for
error on the logistics.
"Everything is off the truck and into place,"
he added. "All deliveries have to be scheduled according to the following
day's activities or the day's activities." With Tindall's erection schedule,
that could mean as few as seven or as many as 15 trucks making deliveries each
day.
It's not like an erector set where all of the pieces are the same,
said Sam Briuglio, Tindall's sales manager.
"Each job and each piece
is a custom-manufactured job and custom-manufactured piece," Briuglio added.
"It's not something we mass-produce in advance, but each piece must be carefully
engineered and marked to be placed in a particular location and in order."
Useful
Source: For a live shot of the construction site, go to: http://www.portno.com/cruise_term.htm
|