| Long Time Coming New
health, recreation facility built into Grambling hillside
By Martin Schwartz It's hard to say how long plans have been in the works
for Grambling State University's new Health, Physical Education and Recreation
Building.
"Jimmy Carter was president when this project was first
proposed," Jerry McMurray, interim associate vice president for facilities
management, said during the groundbreaking ceremony in April 2004.
At that
same ceremony, Grambling State University President Neari Warner called the $19
million project "long overdue."
|
"This new facility is essential in our mission to become
a leading cultural center here in north-central Louisiana," Warner said.
"This project has been in progress for more than two decades and it is a
great day to finally see it come to fruition."
The 137,573-sq.-ft.
facility, being built by Lincoln Builders Inc. of Ruston, will house the university's
HPER Department and serve as a home for the Grambling basketball programs. It
will also serve as a multi-purpose assembly center for the university and surrounding
community. Seating is estimated at 7,500 for sporting events and 9,000 for other
events.
The structure has two levels, including a 96,000-sq.-ft. events
level with classrooms and offices, multipurpose room, banquet areas and weight
rooms; and a 49,000-sq.-ft. second-floor concourse with public restrooms, concessions,
ticket office and a Hall of Fame display area.
Nat Mixon, Lincoln's project
manager, said the facility is being built into a hillside next to the football
stadium and therefore required a lot of groundwork before construction could begin.
He
said crews had to cut 18 ft. deep into the hillside.
"The backside
had a minimal amount of fill, so it was mainly hauled off," Mixon added.
He said about 100,000 cu. yds. of dirt was removed, and "it required
four weeks of steady hauling."
The west side of the building - where
the main entrance leads into the concourse level - lined up with the top of the
hill into which the structure was being built. The ground-level entrance on the
other side of the building opens up one story down.
The structural-steel
building will have a brick and steel-siding exterior and acoustical-metal deck
roof. The bleacher seating on the upper and lower bowl of the stadium is made
of precast concrete and the structure has about 65,000 cu. yds. of cast-in-place
concrete for foundations and decking.
Mixon said most of the construction
has been routine, with the exception of the installation of heavy trusses for
the large span over the arena. The two large trusses span 206 ft. and weigh about
70 tons each, Mixon said. Two smaller trusses reach 106 ft. long and weigh about
35 tons.
Assembling the trusses took more than a week.
"The
big trusses came in like sticks and we had to assemble them," he added. The
preliminary assembly created three big pieces that were spliced together. Web
members were bolted in and torqued and the camber was adjusted, all while the
truss remained laying on its side.
Once all welds were checked and verified,
200-ton cranes - one stationary and one crawler - were brought in to raise the
trusses into place.
"They had it all prerigged the day before and
on the morning of the set it took them (Ranger Steel Erectors of Monroe) about
three hours to get it lifted up and bolted in place," Mixon said.
At
that point, the building started to take shape.
"We had done a lot
of work, but it didn't look like it because we had no structure over our heads,"
Mixon said. "We put those monster trusses up and then put on the regular
smaller roof joist and the roof decking. In a period of two weeks it went from
a wall up to the sky to having a lid over our heads. We weren't in the dry, but
there was a lid."
The building is on target for completion in June.
About
20 subcontractors from across the state have contributed to the job. Steel Fabricators
of Monroe is fabricating the steel structure, Bernhard Mechanical Contractors
of Baton Rouge is providing mechanical systems, B&J Flooring of Shreveport
is supplying flooring and Joe Banks Drywall & Acoustics of Mangham is handling
all drywall services.
This is not the first project Lincoln Builders has
undertaken for Grambling. With offices just 10 mi. down the road, the company
has also completed a computer building, nursing building, intramural complex and
stadium-support facility for the university.
But the HPER complex is by
far the largest project the company has undertaken at Grambling, Mixon said.
The
original architect on the building was AE Design, a company that Mixon said is
now defunct. The Newman Marchive Partnership, a Shreveport-based architectural
firm is administering the job. Those changes took place prebid and haven't effected
the construction, Mixon said.
The building is currently on target for a
June 2006 completion.
"This will be a shot in the arm to our athletic
programs," athletic director Al Dennis said during groundbreaking ceremonies.
"This new facility will make us more competitive with other University of
Louisiana System institutions and historic black colleges and universities around
the country."
Useful Source: For
updates on the project, go to: http://www.gram.edu/Departments/Public%20Relations/pressreleases.htm
|