|
One step closer
Comite Diversion project moves
forward despite funding delays
By Angelle Bergeron
At first glance, the future site of the Lily Bayou Control
Structure near Baker appears to be a huge pit scratched out
of the red dirt.
But B&K Construction of Mandeville's $27 million project
to construct the first phase of the $163 million Comite River
Diversion Project has proven more intricate and exacting than
simply "digging a huge hole in the ground," said
Blake Andrews, B&K president.
James Construction Group of Baton Rouge had a previous contract
to dig the hole and build a slurry track, subsequently moving
more than 1.2 million cu. yds. of dirt, said Philippe Jean,
B&K's quality control officer.
"The current contract requires that we dig the hole
bigger, longer and deeper and build the concrete control structure,"
Jean said.
By the time B&K is finished with excavation, a total
of 2.5 million cu. yds. of earth will have been removed. Maintaining
the proper specifications to shape what will be a long, sloping
basin has been an intricate process.
"It's an ongoing job to keep up with Duett Landforming
(a subcontractor to B&K) and the elevations," said
Mike Tassin, project manager for B&K. "We have to
set the elevations with lasers, and every time you get started
and set up you have to move because it's not a flat hole but
is changing contours and elevations."
B&K began work in September 2004 on the three-year Lily
Bayou project, which is the first of 14 phases in a long-awaited
U.S. Army Corps of Engineers project to address flooding along
the Amite River.
"A lot of the flooding in the Baton Rouge area is caused
by the Amite and Comite rivers," said Dietmar Rietschier,
executive director of the Amite River Basin Commission.
The Comite is a tributary to the Amite, which serves as the
political boundary between four parishes: East Baton Rouge
and Livingston on the south end and St. Helena and East Feliciana
farther north. Over the years, local governments have individually
tried to resolve the flooding issues, Rietschier said.
But because of the magnitude of the problem it became apparent
that a regional, multijurisdictional approach was necessary.
"Of course, when you are dealing with any infrastructure
projects of this magnitude it requires federal assistance,"
Rietschier added.
For about 20 years, the corps has conducted numerous studies,
resulting in several proposals. The corps considered building
dams and elevating properties, but decided upon a diversion
canal that would direct overflow from the Comite to the Mississippi
River, Rietschier said.
The system will originate at the Comite and Amite rivers
and go west toward the Mississippi River near Baker, where
B&K is constructing the Lily Bayou portion.
"The whole thing will be dry until the final phase is
finished," Jean said.
Dirt from the 6,000-ft.-long and 600-ft.-wide Lily Bayou
site is being removed to an adjacent, 100-acre disposal area.
The diversion will consist of an open channel lined with riprap,
which leads to a drop down and widens into a spillway.
"When water equalizes to 38-ft. elevation, it will simply
run off through swampy area the final 2 mi. to the river,"
said Clark Carroll, project engineer for the corps.
Basically, the job requires a "lot of scrapers and a
bunch of well pumps," Tassin said. Aqua Terra of Baton
Rouge installed 70 100-ft.-deep pumps and 20 240-ft.-deep
pumps, Tassin said.
That next phase requires construction of the huge concrete
flume, which will be the centerpiece of the control structure.
By the end of October, B&K had completed construction
of a $2 million batch plant onsite, a necessity for handling
the 1,000-cu.-yd. pours the contractor will be making.
"It's a real slow-curing mix because they don't want
it to crack," Tassin said.
The mix is the corps' "tried and true" mix that
has been used for years on locks and dams, Andrews said.
"We're going to pour slabs from 8- to 14 ft. thick using
regular mass concrete and then top it with a final, 12-in.
layer of slab that is resistant to abrasion and cavities,"
Andrews said. "With all the flow coming through, this
keeps the base of the concrete from getting destroyed."
The pumps must be activated before the contractor can excavate
deeper than 38 ft., shore up with sheet piling and pour the
concrete.
But by the end of October, B&K was waiting on funding
before proceeding to the next phase.
"Once we dewater, we'll be past the point of no return,"
Tassin said. "The next phase is an $8 million chunk,
and it involves a few things that have to happen in sequence,
so the funds must be appropriated for the entire duration."
"Financially, we can't take that next step as a contractor
so, more than likely, we'll stop the job in November or December."
The overall project is scheduled for completion by 2011,
contingent upon federal funding, Rietschier said.
"Allocations issues were being resolved before Hurricane
Katrina, which I feel has demonstrated how important it is
to fund these flood-protection issues in south Louisiana,"
Rietschier added. "I believe at least we should get adequate
funding to keep us going, and hopefully, allocations might
be increased. I feel like we are in better shape than we have
been in recent years."
"Normally, funding wouldn't have been an issue, but
we've been on hold since the war in Iraq," Clark said.
The corps has a commitment from Congress for the project
for $6.2 million beginning in the next fiscal year, which
started Oct. 1, said Larry Poindexter, the Corps senior project
manager for the Comite River Diversion project.
"That isn't enough to take B&K through the entire
fiscal year as he has it scheduled," Poindexter said.
"We're looking to other projects that have the money
but may not be able to execute for the entire year. That may
allow us to divert some of those funds."
Over the years, the corps has diverted some of the funds
dedicated to the Comite project for other needs and "now
we're trying to re-gather some of those funds," Poindexter
said.
The next phase is the Comite River Diversion Project is for
a bridge crossing at Louisiana Highway 67.
"That is already under design," Poindexter said.
"We will let a contract for that is late 2006 or early
2007."
Construction won't be contiguous throughout the 14 phases
of the project, but will hopscotch, Carroll said.
"We have reviewed control structures at other bayous
and some of the highway crossing structures, and some are
still in the design phase," Carroll said.
|