|
TIMED moves on
Hurricanes to have little effect
on program's progress
By Angelle Bergeron
Although Katrina and Rita wreaked havoc throughout Louisiana's
transportation and infrastructure system, DOTD predicts the
hurricanes will have little effect on progress of the state's
three TIMED bridge projects.
The $4 billion Transportation Infrastructure Model for Economic
Development includes widening the four-laning of 536 mi. of
state highways, improvements to both the Port of New Orleans
and Louis Armstrong International Airport and widening and/or
new construction on three major bridges.
Although the Huey P. Long Mississippi River Bridge in New
Orleans is in the hurricane-impacted area, the DOTD is still
on track and let the first phase of the project Dec. 14, said
Dana Newsome, communications director for Louisiana TIMED
Managers.
LTM is the third-party firm that represents the DOTD on all
TIMED projects in regards to finances, communications, overview
and design, even some construction, she said.
"The letting is very significant because it is the first
project continued in the area since Hurricane Katrina and
because it wasn't affected at all," Newsome said. The
first phase includes widening of the piers beneath the bridge
and won't affect traffic flow.
DOTD cannot currently determine whether the hurricanes will
present any delays to new construction of the Florida Avenue
Bridge over the Industrial Canal between Orleans and St. Bernard
Parishes.
"We are still making assessments to the area, which
was incredibly hard-hit, so it is too early to say exactly
how much is going to change," Newsome said. However,
schedule adjustments are likely. "We are still on track
to construct the project and the first letting is scheduled
for January."
Three joint-venture groups have been short listed to prepare
design/build proposals on the St. Francisville Bridge project,
the DOTD's first experiment in the design-build project delivery
method. Those three were given an invitation to submit a design
build proposal by January 2006. Because of the storms, DOTD
postponed the date for receipt of the proposals until March,
said Blaise Carriere, DOTD special projects assistant.
"We delayed on St. Francisville to allow contractors
to see if the subs would be available and just to let things
settle down a bit," he said.
"We are on track to finalize the design build procurement
process in early 2006 and we anticipate at least starting
to see some activity in the area of the bridge by the first
quarter of 2006," Newsome said.
Total cost for the St. Francisville project is $269 million,
which is based on 2005 dollars, Carriere said. The Huey P.
Long widening is $413 million and Florida Avenue is projected
to be $209 million.
"We hope to bring each of those projects in for a lesser
amount of money," Carriere said. DOTD has projected completion
of the TIMED program by 2010.
|