|
Moving forward
LA 1 project becomes more important
than ever
By Angelle Bergeron
The replacement of the perpetually-flooded La. Hwy. 1 has
been a nagging, lingering project for DOTD for some years.
Traversed by a relatively small population of fishermen and
vacationers destined for Grand Isle, the artery hasn't received
the sort of high-profile attention bestowed upon some metropolitan-area
projects.
But the road that connects Golden Meadow to Grand Isle and
Fourchon is an integral artery that supports 70 percent of
the offshore oil industry in the Gulf of Mexico and supplies
18 percent of the nation's hydrocarbons. Also nearby are two
of the most productive estuaries and fishery ports in the
country, said David Miller, DOTD project engineer.
If the need to evacuate residents of Louisiana's only inhabited
barrier island wasn't sufficient rationale for the $300 million
project, the squeeze placed on the nation's oil supply in
the wake of hurricanes Katrina and Rita was a reminder of
the project's significance.
"The project is even more vital since Cameron and Venice
are shut down," Miller said.
The 2- to 4-ft. elevation highway "literally floods
all the time," he said.
The project, which was designed to include 17 mi. of four
elevated lanes, was let for bid in June. Only two joint-venture
bids came in for the enormous project, both at close to $100
million over DOTD estimates.
"We went back and did some checking and talking about
what happened," said Michael Bridges, undersecretary,
Office of Management and Finance. First of all, the contractors
didn't think there was enough time allotted for construction
of the project, Bridges said. "They had to put multiple
crews and overtime, and that put the price up."
Additionally, several components of the project could only
be provided from one contractor, who was busy providing almost
all of the components for the Escambia Bay Bridge project.
"It was a simple supply and demand problem," Bridges
said.
Furthermore, DOTD had advertised the project for only a month,
which contractors said didn't allow enough time to explore
issues like setting up a concrete plant and providing housing
for crews. The size of the project also limited contractors'
bonding ability, shrinking the field of bidders. "They
basically built risk into their bids," Bridges said.
The DOTD took all of these considerations into account and
divided the project into three phases, the first of which
was let for bid in December. "We simplified it, split
it up into three pieces because we feel like the smaller packages
will encourage more competition," Bridges said.
Phase B (the first to be let) includes construction of approaches
to Bayou Lafourche Bridge in Leeville and T-intersection connectors
(originally envisioned as turning lanes with off ramps) north
and south of Leeville. "We decided to remove all of that
overbuilding, and we could always come back and add those
turns if and when the final two lanes are complete,"
Bridges said.
Phase A, which will be let this month, includes the elevated
bridge from Leeville to Fourchon. DOTD opted to go with a
smaller piling, which will be more readily available from
a variety of manufacturers. Phase C, which includes the Bayou
Lafourche crossing will be let in February.
A major component of the project is the toll plaza area,
part of Phase B, and the reason for that being the first portion
constructed.
"The reason why tolling was considered for this was
that the locals realized they would never get enough funding
for this roadway without putting up some money," Bridges
said. Businesses from Port Fourchon and Thibodaux formed a
group called the LA1 Coalition, and they determined that we
could raise some of the money for this project through tolling.
"DOTD was able to put together a plan that utilized
tolls, state highway funds and federal funds," Bridges
said. "The plan of finance included the sale of bonds
based on revenue derived from those tolls, which raised $136
million."
DOTD has also extended the construction schedule substantially
and added a $10,000 per day up to $5 million incentive for
Phase B.
The whole project is scheduled for completion by late 2010.
|