|
I-10, Evangeline Thruway gets makeover
Lafayette concrete projects endure rain, traffic
By Sam Barnes
When work began to build the embankment for a new Lafayette
interchange last summer, the contractor looked forward to
south Louisiana's traditionally dry Fall days. Little did
they know that two hurricanes and a tropical storm would converge
on the state to create the wettest season on record.
This, coupled with having to work along one of the busiest
stretches of I-10 in the state, necessitated a highly adaptable
schedule and a malleable traffic management plan.
At the outset, James Construction Group's $19 million Louisiana
Avenue Interchange project required the placement of more
than 250,000 cu. yds. of material to build up the interchange,
as well as to construct a new embankment for a 1-mile stretch
of realigned Louisiana Avenue that will run beneath it.
The rain, said Project Manager Nick Cross, proved to be both
a help and a hindrance.
"It was quite challenging, with the weather and everything,"
Cross said, "since we were working in a bottom with no
drainage." The James crew "cut lime" into the
soil to dry it out as they came up with the embankment.
Attempting to develop an innovative way to make up for lost
time, the James Construction crew greatly reduced compaction
time by doubling the amount of surcharge placed on top of
the interchange embankment from 3 ft. to 6 ft.
"By doing that, we cut the compaction time in half and
moved the entire schedule up by several months," Cross
emphasized.
Ironically, the rain also helped speed compaction times.
Traffic maintenance has "been difficult," he continued,
pointing to the high traffic count on I-10 as part of the
reason. Crews have to maintain two lanes of traffic at all
times.
"We built the ramps first, and once we got the ramps
built and a detour built, we dropped traffic on top of that.
We then removed existing eastbound I-10 and started work on
the eastbound overpass," Cross said.
Despite weather and traffic related problems, the crew has
remained on schedule, with only about 80 of the 440 contract
days remaining (in March) and a required June 15 deadline
easily within reach.
According to Bill Fontenot, DOTD district engineer administrator
in Lafayette, upon completion the crew will have built twin
overpasses, measuring about 1,400 ft. each, that will span
over the realigned Louisiana Avenue. The interchange will
also have four off- and on-ramps, each measuring about 300
meters in length.
"About half a mile of Louisiana Avenue is also being
relocated and turned into a four-lane road," explained
Fontenot.
"There'll be two lanes north and southbound, as well
as a median in the middle."
At present, the existing two-lane avenue runs beneath the
Old Vermilion Bridge to the east of the new interchange.
During the overpass construction, the James Construction
crew followed the embankment by driving precast concrete piles
measuring 50 ft. long and 14 in. sq. as support for the structure.
After the piles were capped with concrete, columns averaging
48 in. dia. were formed and poured as support for the overpass
decking.
"About eight piles were driven for each overpass bent,
and there were a total of 28 bents for both overpasses,"
Cross said.
Gulf Coast Pre-Stress Inc., Pass Christian, Miss., supplied
the piles and bridge girders.
"Most of the girders were Type 4 (a standard DOTD specification)
and reached about 86 ft. long," he continued.
Concrete placement atop the new overpasses proved challenging,
since the decking required an 8-in.-thick layer of ready-mix
to be pumped from the water-drenched ground below.
As a result, pours were often delayed due to inclement weather.
"The weather and lack of drainage (the drainage system
wouldn't be installed until later) created challenges, but
we overcame them," Cross said. All of the paving was
reinforcing with a double matting of reinforcing steel.
Drainage installation includes a variety of new catch basins
and concrete drainage pipe to accommodate both the interchange
and the new section of Louisiana Avenue.
Leading to the overpasses are approach slabs ranging from
850 ft. long in the eastbound lanes to 1,500 ft. in the westbound
lanes. Barrier rail construction will be the final stage of
the interchange project, performed by Ray-Bar Contractors
Inc., Baton Rouge, in April.
Other work at the site includes the widening of the Vermilion
Bridge to the east by about 12 ft. to accommodate acceleration
and deceleration lanes that are necessary for the new overpass.
"For the new Louisiana Avenue section, we presently
have the new embankment complete and expect to begin putting
down the base in late March," said Cross. The new roadway
will consist of 8.5 in. of limestone, a 2-in. asphalt base
and 9 in. of concrete paving. Paving is expected to move relatively
fast, since traffic considerations are not a concern, with
completion expected this summer.
Before work began at the site, the area had been occupied
by a forested area and a crawfish pond that had to be "mucked
out."
Evangeline Thruway. Where traffic has been a concern at the
Louisiana Avenue overpass, it was a "nightmare"
on a surface street project to the west, where James Construction
Group is adding lanes and patching existing pavement on Evangeline
Thruway.
One of the most heavily traveled stretches of road within
the city limits of Lafayette, the thruway was overcrowded
and thus required the addition of one to two lanes in each
direction.
The site stretches 1.8 miles south of where the thruway meets
I-10.
"To accomplish the task, it required a lot of pre-planning,"
Cross said. "We have a full time traffic crew that moves
everything around for everybody.
"And when unexpected things come up, we work it out
together. I've done a lot of work in traffic management, and
so have the other supervisors. That experience helps us."
One of the most advantageous decisions was to perform all
of the concrete paving at night, which allowed the crew to
shut down the roadway to one lane in each direction while
not significantly affecting traffic.
Beginning at 8 p.m. and lasting until 5 a.m., the crew poured
virtually all of the 10,000 cu. yds. of concrete required
for the job, supplied by Angelle Concrete Inc.
Major intersections proved difficult, since traffic had to
be routed to the shoulder during the paving operations.
"When we were working in certain lanes, we would have
to split the traffic and move them to the shoulder to get
them around," Cross said.
James Construction crews added one to two lanes in both the
north and southbound lanes.
Upon conclusion of the project this spring, "there will
be at least three lanes the entire length of the site in both
the north and southbound driving lanes, and in some places
it will be five lanes (for turning lanes and intersections)."
Before constructing the new lanes, however, the crew performed
"a lot of patching" of the existing concrete roadway,
as well as cleaning and re-sealing of all existing pavement
joints.
"There were also a lot of catch basins and manholes
to remove to make way for the new lanes, followed by new catch
basins and piping," Cross continued.
According to Cross, about 11 in. of jointed concrete was
placed for all the new lanes, on top of an 8-in. base of Florolite.
The jointed paving was reinforced with dowel baskets, and
tied to the existing pavement.
"We had to do an excessive amount of drilling to tie
the slabs together," Cross said.
|