|
Leading the pack
State's biggest project facilitates ExxonMobil compliance
By Sam Barnes
When ExxonMobil Site Execution Leader Raymond Fugler evaluated
the refinery's effort to desulfurize its gasoline early in
the design phase, his biggest concern was a heavy lift that
wouldn't occur for more than a year.
Members of the construction team were brought into the development
phase of the Baton Rouge project in 2001 to create construction
efficiencies, and foresaw the lifting of the 500-ton T800
process vessel as the project's biggest logistical test.
"We performed a lot of heavy-lift, heavy-haul planning
and the T800 was our primary concern," Fugler said. "We
had to find a way to get the 500-ton vessel to the jobsite
in the middle of an existing refinery with low pipe racks
and numerous obstructions. That was the critical issue from
the beginning."
The vessel is a primary component within ExxonMobil's $280
million low sulfur mogas (clean gasoline) project, which will
enable the plant to produce low-sulfur gasoline by 2004, as
mandated by the Environmental Protection Agency.
Making a path for the vessel proved a formidable task.
"To get the vessel underneath piperacks we had to dig
an 18-in.-deep, 400-ft.-long trench right down the middle
of the road," Mike Reed, Fluor Daniel site manager, explained.
"That way we could successfully drive the vessel in a
horizontal position beneath the racks." Fluor subcontractors
J.E. Merit Constructors and Deep South Crane & Rigging
removed obstructions and some facilities to "clear the
path," including a storage yard and signage.
"There were also a few underground sewers and other utilities
that were re-routed because they couldn't hold up under the
weight of the vessel," he said.
According to Reed, the lift of the T800 was actually the final
stage in the vessel's long journey, which began with its manufacture
last year. The 178-ft.-tall vessel was transported by ocean-going
vessel to a New Orleans docking facility, then barged by Deep
South to a dock off the Mississippi River in Baton Rouge.
Jason Ribes, project manager with Deep South Crane & Rigging,
Baton Rouge, said a similar procedure was followed for each
of his company's major lifts, but that the T800 was by far
the most difficult.
"When we unloaded it, we put the vessel on stands to
allow our transporter trailers to get beneath it. The transporter
then hydraulically jacked itself up by about 6 in. or so and
picked up the load," Ribes said. The 40-axle transporter
drove the vessel to the ExxonMobil site 3 mi. away.
"We had to remove some traffic lights, so the city required
we transport the vessel on the weekend," Ribes said.
Once the vessel had maneuvered through the existing plant
and arrived at the jobsite, it was placed in an area where
it could be "dressed out" with platforms and insulation
during a month-long process.
Although T800 was the heaviest of the vessels to be lifted,
10 other heavy lifts will be required before the project's
end in November, four of which weigh more than 200 tons (most
notably some 225-ton reactors). Deep South is performing all
the heavy lifts, using a 1,500-ton capacity crane and a 750-ton
tailing rig.
According to ExxonMobil's Wayne Purdom, site startup manager,
the project's ultimate purpose is to enable the Baton Rouge
plant to begin producing gasoline with reduced sulfur (less
than 30 parts per million) by Jan. 1, 2004.
"The project maintains the refinery's ability to produce
gasoline. Without this project, there would be an approximate
30 percent reduction in the amount of gasoline the plant could
produce," Purdom said. The project uses SCANfining technology
developed by ExxonMobil engineers in Baton Rouge, which reduces
sulfur content in gasoline while maintaining octane level.
This proprietary technology has been sold to other refining
companies as part of efforts to reduce sulfur in their own
fuels.
The design portion of the Engineer/Procure/Construction contract
began in 2001 (performed by Fluor engineers in Houston and
New Delhi, India), and construction broke ground at the site
in June 2002. Five months of demolition had already been performed
by ExxonMobil's continuing service contractors (Harmony, IMR,
Basic, Brand & ISC), allowing Cajun Constructors Inc.,
Baton Rouge, to immediately begin constructing more than 600
drilled piers ranging from 24 to 36 in. dia. and averaging
18 ft. in depth.
Weather related obstacles were encountered during the foundation
phase, as two hurricanes shut the jobsite down for weeks,
requiring that the subcontractors work "select overtime"
to maintain the schedule.
According to Reed, the desulfurization project is not confined
to just one area within the massive plant, but instead is
spread across several locations, including a grassroots plant
area, a process area, a network of interconnecting piperacks,
a new flare and a new caustic area, and two existing naphtha
hydrofiners.
"As part of the demolition phase, the contractor had
basically 'bathtubbed' the grassroots area by leaving a 4-ft.-deep
hole," Fugler explained. "This allowed us to put
in underground piping and utilities, then backfill as we moved
up with the plant. It basically eliminated a lot of excavation
that we would've had to do otherwise."
Approximately 900 cu. yds. of concrete were placed for the
drilled shafts and for several large mat pours necessary to
support the vessels.
"The largest foundation was built for the T800 vessel.
That's the big boy. It reaches about 4 ft. in depth,"
Reed said. Upon project completion, approximately 8,300 cu.
yds. of concrete will have been supplied by Dolese Concrete,
Baton Rouge, with the civil work being performed by Boh Bros.
Construction LLC.
The foundations will eventually support more than 130 pieces
of equipment interspersed throughout the multi-faceted jobsite,
consisting of exchangers, pumps, drums and reactors in a variety
of sizes and shapes, as well as a three-cell cooling tower.
Structural steel is being used heavily during construction,
with about 2,100 tons of steel being erected by Performance
Contractors, Baton Rouge.
"We've got a mixture of galvanized and fireproofed steel,
but we didn't have any intricate type material. It's pretty
vanilla stuff," Reed said.
Pipe installation comprises another significant portion of
the project, with more than 175,000 linear ft. of carbon,
stainless steel and chrome piping reaching up to 36 in. dia.
installed by Performance crews.
In another example of constructability at the site, a new
electrical substation is being delivered in four separate
modules, then "simply set on top of its foundation and
bolted together."
The package substation "took all of the manhours off
the site," Reed said. MMR Constructors Inc., Baton Rouge,
is performing the electrical and instrumentation installation
within the control building, as well as throughout the remainder
of the plant.
According to ExxonMobil's Purdom, once the project is completed
in November, the refinery owner will be responsible for the
startup of the facility. Throughout the project, some turnarounds
have been necessary to tie in new piping with existing equipment.
At the peak of construction, about 900 workers - Fluor contractors
and ExxonMobil subcontractors - will be working at the site,
expected by late Spring.
More than halfway through and no OSHA incidents.
Now that the project is well over halfway complete - about 1,100,000
of a total 2.1 million manhours - a lack of OSHA-recordable
incidents or injuries has the construction team optimistic
that it could go the distance.
"We have to say that what we're doing here is extraordinary
by any jobsite's standards," noted Fugler. "Our
goal is that nobody gets hurt. That is the highest standard
and we will not be satisfied with less."
Reaching the zero-incidents milestone has not come easy, with
Fluor and all subcontract companies making a concerted effort
at the project's outset to align with ExxonMobil's safety
philosophy.
"I think the biggest thing is the presence of management
in the field every day," Purdom said. "We've developed
a culture with the craftspeople here - the safety culture
is part of our everyday business."An awards program is
used in the field to reward employees for safe practices "on
the spot." Employee meetings, which allow employees to
talk about issues that might compromise the safety of the
jobsite, complement this proactive approach.
Ninety-five percent of the subcontractors at the site are
based in Louisiana.
|