|
Northwest Regional Report
Region turns to universities, tourism, public projects
By Sam Barnes
Although the cities of Shreveport and Bossier City have been
the shining lights of the northwest region, the remaining
municipalities in the quadrant have earned the right to toot
their horns, too.
Natchitoches, the area's next largest municipality, supports
a healthy level of construction investment that comes from
a variety of areas.
Nick Pollacia, executive vice president of the Natchitoches
Area Chamber of Commerce, said Natchitoches continues to derive
much of its revenue from Northwestern State University, the
tourism industry and state-funded projects. The new Red River
port is also gradually attracting new industry.
"Natchitoches continues to develop itself as a major
tourism destination - the Ft. St. Jean Baptiste State Commemorative
Area has a new interpretive center being built as part of
that in the middle of downtown," Pollacia said.
A record enrollment at Northwestern this past school year,
as well as increases in employment up to 800 employees at
Alliance Compressor, have buoyed sales tax revenue.
"We've been able to maintain stability thanks to all
this, despite the overall economic conditions," he said.
He said the creation of a new Natchitoches Economic Development
Commission in 2001 has already resulted in the attraction
of new industry to his area, which eventually leads to new
construction opportunities.
"This (EDC) is run out of the mayor's office, and we
think it's going to be a tremendous resource," he said.
"Its number one benefit is that it will have more power
to accomplish things by working through the mayor's office,
and it puts more people and emphasis on economic development.
Chambers of Commerce can't always attract that kind of involvement,"
The EDC will also work with workforce education and development.
The Natchitoches area has several potential construction investments
itemized in Louisiana's Capital Outlay Budget, although these
are far from receiving guaranteed funding.
Following are some significant construction projects currently
under construction across the northwest region.
Demon Wellness Center, Northwestern
State University. Construction crews can be seen crisscrossing
the Northwestern campus, with multiple renovation projects
in varying stages of construction.
The largest project - the $6.6 million renovation and expansion
of the Demon Wellness Center - will result in a 21,000-sq.-ft.
extension to the facility that will eventually support a new
weight room, cycle room, handball court and running track.
The facility is designed by Slack, Alost, McSwain & Associates,
Shreveport.
A. J. Loga, jobsite superintendent with Don Barron Contractor,
Farmerville, the project was in the early stages of construction
in May, when crews demolished portions of the existing building
to make way for the new extension.
"Technically, the new building has three levels,"
he said. "It will have a basement, a ground floor and
a balcony (with a running track) around the whole building
and through the new addition."
The basement area will contain locker rooms, weight rooms
and workout areas, while the second level will support offices.
"When we start new construction, we'll first construct
96 drilled piers for the basement area," Loga added.
The structure will be built with concrete block, brick and
EIFS.
Morrison Hall and Consumer Sciences
Building (renovation), Northwestern State. Nearby,
two buildings that share a courtyard are being renovated simultaneously
by Natchitoches-based RDS Construction Inc.
Ronald Smith, RDS president, said the $4.2 million project
requires the renovation and re-roofing of the two-story masonry
Morrison Hall and the Consumer Sciences Building, as well
as installation of a new chiller unit and tower and the demolition
and re-building of the courtyard between the two buildings.
The buildings were originally constructed in the late 1940s.
"Both buildings were completely gutted out, except for
the staircases," Smith explained. "New elevators
were put in each and new walls went back up. I'd say we're
about 80 percent complete. This thing is going to be gorgeous."
Architect Wayne Coco with Coco & Co., Simmsport, designed
the renovations, and construction broke ground in December
2002.
"We were fortunate that there was no structural damage
we had to contend with," Smith said. "These are
well-built, pan-formed buildings that were rather costly to
build in their day." RDS crews discovered old 1940s-era
newspapers "stuffed into the voids of the pan forms"
that were used to prevent the concrete from running out of
the voids."
Exterior work was minimal, with the brick "pointed up
and waterproofed" and some exterior components removed,
refurbished and replaced.
"There's a lot of coping and stone on the project. The
pieces that were broken were matched and replaced," he
added.
JRT Operations Facility, Fort Polk.
The Orlando office of VOA Associates Inc., architecture,
planning and interior design, recently announced that construction
is underway on an extensive renovation project to convert
a five-story barracks building into a U. S. Army headquarters
building at Fort Polk.
VOA is providing full architectural/engineering services,
partnering with Gibbs Construction, New Orleans, on the design-build
contract for the headquarters Joint Readiness Training Center,
formerly known as Building 350 at Fort Polk. The $10.6 million
renovation is scheduled for completion by January 2004.
Ted G. Fery AIA, principal with VOA and director of the firm's
Military Design Program, said the 81,300-sq.-ft. project will
consolidate the operations of The Army Joint Readiness Training
Center and the Fort Polk Headquarters, creating a modern executive
center for the post.
"The building was originally used for housing bachelor
officers located at the installation," Fery explained.
"Upon completion, the new building will consolidate approximately
19 different departments into one facility."
Consolidated Library Building, Fort
Polk. Dual buildings joined by a common lobby are under
construction at Fort Polk, to ultimately serve as a new consolidated
library and two-story education center.
Both structures, costing about $10 million, are being constructed
of structural steel and masonry by Roy Anderson Corp., Gulfport.
Work began in December.
"We are roughly about 40 percent complete, with the steel
up and the slabs on the education building already poured,"
indicated Mark McDaniel, senior project manager. "We're
now starting the steel studs and masonry." A majority
of the buildings' exteriors consist of concrete block and
brick, with some stucco above the window areas.
An atrium-style structure, also made of steel, connects the
two buildings.
McDaniel said that approaching the project in design-build
fashion has enabled the contractor to maintain the schedule
despite the fact that the design was incomplete at groundbreaking.
Studio South of Gulfport, Miss., is the design firm used by
Roy Anderson at the site.
"The design started in August," McDaniel added.
"We did a preliminary design, a technical proposal first,
then a preliminary set of drawings, and each time we did that
we had a meeting. We minimized changeorders that way.
The contractor is engaged in several other military projects
across the country being coordinated in similar fashion.
South Toledo Bend State Park, Sabine
Parish. Leesville contractor Pat Williams Construction
is in the middle of constructing 25 small wood-framed buildings
in the middle of the piney woods at Toledo Bend Lake. The
project will ultimately construct a new $8.6 million South
Toledo Bend State Park.
Project Manager David Delrie said most of the structures are
1,200-sq-ft. cabins that are interspersed throughout the 380-acre
park, located at the southern tip of the lake.
"Right now (late May), we're in the full thrust of the
project," Delrie said. "We've got about seven buildings
under construction and we're pouring either a footing or a
slab every week. Of the 25 buildings, 24 are wood-framed,
with one pre-engineered metal building to serve as a maintenance
facility."
Nineteen of the buildings are "cookie cutter" cabins,
with the remaining wood buildings to serve as a comfort station,
restroom buildings, a fee booth and a manager's residence,
he added.
Completion of the entire project is scheduled for July 2004.
Early in the project, earthmoving in the hilly terrain presented
the greatest challenge for the contractor.
"This is hill country, and to meet DOTD specs a lot of
cut and fill had to be done - mostly during bad weather,"
Delrie said. "Early-on, everything hinged on the roads
being passable for the concrete trucks (although none of the
paving will be done until later in the project)."
The 3-mile network of roads will be constructed of lime, soil
cement and asphalt, with some crushed stone.
Natchitoches Parish Hospital addition.
A new $10.4 million, 65,000-sq.-ft. outpatient facility
adjacent to the existing Natchitoches Parish Hospital broke
ground in late 2002, becoming the largest building project
in many years for this northwest Louisiana town.
The project will also include approximately 35,000 sq. ft
of renovations to the existing hospital, to be performed once
the new addition is complete.
Carl Riche, vice president of general contractor Skip Converse
Inc. of Pineville, said the new two-floor outpatient hospital
will be physically connected to the existing seven-story hospital's
first and second floors.
Site demolition, including the removal of existing parking
areas, began last Fall, and was followed by the installation
of 300, 40-ft. deep, 18-in.-dia. auger cast piles by L. G.
Barcus. A 5-in.-thick concrete floor slab will then be placed.
Structural steel, being furnished and installed by Confab
Engineering, Shreveport, began erection in late spring, with
"topping out" by the end of the Summer.
The exterior of the structure will consist of stucco, glass
and glazing.
"The building will also have four elevator and stair
towers, although they will be made of poured-in-place concrete,"
Riche said.
Upon completion, the new addition will contain several operating
rooms, some procedure rooms, several treatment rooms, as well
as an Intensive Care Unit area. The radiation treatment rooms
will be encased with lead-lined sheet rock.
"We'll probably average anywhere from 50 to 80 crewmen
throughout much of the project, with the entirety of the project
expected to be complete by the second quarter of 2004,"
Riche said. "That's when the renovation work will begin."
Renovations to the existing hospital will convert areas that
had previously served as outpatient services into expansion
of existing departments. A significant amount of interior
demolition will occur during the process, with renovations
complete by the end of
|