|
A precast solution
Garage doubles parking spaces at community college
By Sam Barnes
Design-build contractor Milton J. Womack Inc. had to find
a solution fast when given only eight months to build a $9
million, 920-space parking garage at Baton Rouge Community
College.
While the design-build approach would help the contractor
more effectively manage the schedule, it wouldn't be enough
to complete the garage by August.
"We began examining the project as both schedule driven
and price driven and decided precast concrete was our best
bet since pouring ready-mix and allowing for curing times
would have created unacceptable delays," project manager
Dale Phillips said.
|
It appears to have been the right choice. The parking garage
structure opened in time for the school's fall semester.
In early January, Milton Womack and architect Robert M. Coleman
& Partners of Baton Rouge met with representatives of
precast supplier Tindall Corp. of Biloxi, Miss., to outline
the project's requirements.
"A week later, our in-house engineering and estimating
staff presented preliminary proposal drawings and pricing,"
said Andrew Wise, Tindall vice president and general manager.
"The architect did the design, sketches, elevations and
designs and we engineered it and put the pieces together."
Tindall supplied 788 precast, prestressed concrete pieces
for the five-level garage, all produced at its casting yard
140 mi. away.
Tindall's technical sales representative, Sam Briuglio, said
precast was the obvious choice for such a fast-paced project.
"It offers a competitive price and extremely fast erection,"
he added. "We pre-produced it at our plant and it was
ready to go when it arrived at the site. When you cast in
place, there's a curing period, floor-to-floor."
Casting began in March "and by the end of April we were
erecting." The last precast piece was placed in June.
A wide variety of precast members were cast, including 10-ft.-wide
"double Ts" that support the garage flooring; 24-in.-sq.
concrete columns; aesthetic arched spandrels for the garage
exterior; stair and elevator tower walls; and ramp walls.
Special customized forms for the arched spandrels had to be
ordered from Helser Industries of Portland, Ore.
"Once we gave Hesler the requirements, they had the forms
here in less than four weeks," Wise said. "We placed
them in our existing flat casting beds."
The spandrels not only create an attractive exterior for the
parking garage but also support the deck double-Ts.
"It's not that common for a precast member to serve an
aesthetic purpose while also maintaining structural integrity,"
Wise added.
During the casting operation, Tindall used high-early-strength,
6,000 psi concrete for most of the pieces. The high-early
mix allowed Tindall to cycle its forms daily. All of the precast
pieces were reinforced with prestressing tendons stressed
at 30,000 lbs. per strand.
Womack's Phillips said that when construction began in January
an existing asphalt parking lot was left in place to prevent
inclement weather from muddying the jobsite and delaying the
schedule.
"We trenched continuous spread footings and drove 55-ft.-long
timber piles right through it," he added. "The precaster
followed behind us."
Erection of the precast was subcontracted to Precast Erectors
Inc. of Hurst, Texas.
"The precast pieces were erected as they came in each
day," Phillips said. "Due to a lack of space, we
could only accommodate about four trucks at a time. That forced
them to keep things moving."
Ready-mix measuring 5 in. and 6 in. thick was placed on top
of the double-Ts for the garage decks, performed as a "turnkey
pump, place and finish job" by Quality Cement Finishers
of Baton Rouge. The company also poured perimeter curbs and
sidewalks with concrete supplied by Heck Industries of Baton
Rouge.
Phillips said the exterior of the garage had some ornamental
brickwork on the bottom half of the arched spandrels and the
entire height of the stairwells.
"This was designed to match the existing buildings on
campus," he added. "Also, all of the concrete surfaces
were painted by Lancorp of Baton Rouge."
Other work at the site included the installation of electrical
and plumbing, bronze railing and slate roofing on the three
stair towers.
Phillips said managing multiple contractors and a 75-man crew
was the greatest obstacle to meeting the stringent deadline.
"Lines of communication had to remain open, and everything
had to be coordinated precisely," he added.
Useful Information:
For listings and descriptions of other precast parking garage
structures recently completed across the country, go to:
http://www.pci.org/markets/markets.cfm?path=parking_decks&id=award_willow.cfm
For more information about design-build, go to:
http://www.dbia.org/
|