|
An ultraviolet solution
Project improves capabilities,
links Shreveport plant to remote control center
By Sam Barnes
Shreveport's north wastewater treatment plant is getting
a $24.6 million high-tech facelift that will enhance its treatment
processes and allow the plant to be remote-controlled.
Critical to the project is the construction of a new ultraviolet
treatment system that will reduce the plant's dependence on
chlorine.
Max Foote Construction Co. Inc. of Mandeville began construction
at the site in September and should finish the project about
six months ahead of schedule in early 2005. Camp, Dresser
& McKee of Baton Rouge designed the project.
"We knew the winter months would probably be rain-soaked,
so we began by performing our biggest excavation and installing
a dewatering system," said on-site project manager Billy
Lott. The de-watering system consists of wellpoints every
8 to 9 ft. connected to a pump that lifts the water up and
over the levee that surrounds the plant.
The strategy appears to have paid off. By the time a wintertime
deluge hit the site in February, most of the plant's new structures
were out of the ground.
"We took out a little more than 30,000 cu. yds. during
the excavation," Lott said. "Some of it was stockpiled
for backfill, but a lot of it we hauled off site." The
six-week excavation was necessary to make way for two 110-ft.-diameter
clarifiers that will perform end-stage treatment of the wastewater
before it is transported by pipeline to the Red River a mile
away.
A ductile iron return-sludge line was installed beneath
the clarifiers to send solids to a nearby pump station and
more than 500 18-in.-diameter auger cast piles were drilled
as foundation.
"Berkel & Co. (Austell, Ga.) ran its auger down
20 ft. and pumped grout through the center tube," Lott
said. "They continued pumping as the auger was lifted
out of the hole." Reinforcing steel was placed into each
shaft with hooks at the top to connect to the clarifier slab.
As each shafts will augered, the resulting displaced soil
was removed by a trackhoe.
Lott said the concrete clarifier walls - completed in March
- are about 22 ft. tall and 18 in. thick. The 1-to-12 sloped
clarifier slabs are 2 ft. 4 in. thick.
"Everything is reinforced with a double matting of reinforcing
steel," he added.
About 6,000 to 7,000 cu. yds. of 4,000-psi concrete is being
supplied for the entire project by Builders Supply Co. of
Shreveport.
Justin Haydel, an engineer with Camp, Dresser & McKee,
said the plant's new ultraviolet treatment system will enable
the plant to meet new treatment requirements mandated by the
Environmental Protection Agency.
"Everybody's getting away from chlorine," Haydel
added. "With the UV system we should significantly reduce
our dependence on the chemical."
The 20-year-old plant is also getting a major electrical
upgrade by Feazel Electrical Contracting of Shreveport that
will connect the plant to the City of Shreveport's System
Control and Data Acquisition system.
The SCADA system will allow city engineers to operate the
plant remotely from a control center on the south side of
the city. All of the city's plants will eventually be linked
to the system.
"This requires a lot of electrical work, including the
construction of a couple of electrical buildings and a lot
of underground electrical installation," Haydel said.
Edison Automation of Nashville, Tenn., will perform necessary
SCADA-related instrumentation within a new 1,378-sq.-ft. concrete
block control building.
In other work, the contractor is converting an existing
oxidation treatment area into an aeration basin by gutting
two concrete tanks, erecting 15 12-in.-thick concrete baffle
walls and installing aeration equipment.
"The aeration basin will consist of coarse bubble and
fine bubble diffusers," Haydel said. "At each diffuser
you have a saddle that connects to a PVC pipe." Air for
the diffusers will come from four blowers being installed
by Max Foote at one end of the basin.
A second oxidation area will remain in operation until the
new aeration basin is operational, then will be taken out
of service.
"We're also gutting an existing screw pump station
and installing six new pumps, and replacing the headworks,"
jobsite superintendent A. E. "Bubba" Ash said. The
pump station is the first step in the treatment process and
"lifts" the liquids from the solids as the wastewater
enters the plant.
Other work requires the intallation of sludge transfer pumps
and associated piping and the conversion of existing final
clarifiers into sludge holding tanks.
"The sludge transfer pumps will take the sludge from
the holding tanks and pump it to belt presses (which 'presses'
the water out)," Ash added. The dry sludge is conveyed
to a dumpster and hauled away.
New ductile iron pipe is necessary to connect new structures
with existing parts of the plant, while some stainless steel
pipe is being installed between the blowers in the blower
building.
"We're placing a 48-in.-diameter ductile iron pipeline
through the levee to tie into the existing pipeline (that
exits the plant)," Lott said. A "T" in the
new line will accommodate a second pipeline to be installed
during a future contract.
Max Foote expects to finish the project in January, about
six months ahead of schedule. Lott attributed the impressive
progress to the "generally good weather we experienced
through January."
"As of right now, we should hold pretty true to that
schedule," he added. At peak this spring, there will
be about 60 contractors at the site.
Another project currently in planning will install a new
high rate clarifier, new headworks and new pump station at
the north plant for about $13.8 million. The project will
be completed by 2008.
|