|
Re-building Bayou Bourbeux
Contractor paves steep Opelousas
canal with low slump mix
By Sam Barnes
A 1.5-mile steep-sloped canal passing through Opelousas is
getting some much needed cosmetic surgery that will accelerate
stormwater flow beginning next year.
The $7.1 million Bayou Bourbeux contouring and paving project
is part of a Natural Resources & Conservation Services
flood control and restoration program and is expected to alleviate
flooding problems for southwest parts of the city.
"This is the last phase of a four-phase flood control
initiative in the Opelousas area," NCRS resource conservationist
Dexter Sapp said. "Preliminary research identified the
canal as a major obstacle to flood control."
NCRS provided $7 million for the canal's construction and
the state provided the remainder through its Capital Outlay
Program.
While design of the project was performed by NCRS engineers,
many decisions are being made "in the field" by
Circle Inc. of Belle Chasse to accommodate changing conditions.
Project manager Matt O'Brien said his crew broke ground
at the weather-plagued jobsite in November, so contending
with a jobsite soaked in wintertime rains was the immediate
concern.
"Since finishing clearing and grubbing, we've had nothing
but rain," O'Brien said. "This is especially problematic
when working in a drainage canal. A sudden rainstorm can wash
away your sand and gravel bedding material and you just have
to write that off as a loss."
To make matters worse, contract specifications required
the contractor start on the downstream end of the canal.
"We're supposed to be pouring 90 ft. a week, and from
January until early March we've poured a total of only 180
ft.," O'Brien said.
This forced the contractor back to the drawing board.
"To speed the concrete placement, we're looking into
different things," he said. "We're pumping it right
now, but it's a very slow process because we must have a special
low-slump mix to flow through the pump. It's taking us eight
hours to make a 30 ft. pour."
The contractor will likely begin placing the concrete with
a crane and bucket.
"Bucketing the concrete is a little more labor intensive
but it will speed production and help us make up some lost
time," he added.
Jobsite superintendent Keith Lua said the crew has also
been "blowing" a ¼-in. layer of gunite onto
the canal bottom and slopes to keep the bedding from washing
away during rain events.
"It gives us a protective covering over the bedding
until we pour concrete," Lua said. "With the rain
we've had, the fill can wash away easily. We're prepping the
bottom with gunite, then coming back and pouring the slabs."
Gunite, also known as shotcrete, is a dry concrete mix distributed
through a rubber gunite hose and placed by air pressure.
The contractor's next major hurdle will come this summer.
"The canal goes through some tightly-compacted residential
areas," O'Brien said. "The most difficult part of
that will be getting equipment access from both sides of the
canal."
For one 1,700-ft. section of the canal, access to both sides
will be impossible.
"The close proximity of residential properties will
force us to work from one side, so it's going to get crowded,"
he said. "Once we get to that area, we'll have to bring
in some larger equipment like a 14-ton cherry picker and long-reach
excavators to be able to reach the entire canal from one side."
Ultimately, the meandering Bayou Bourbeux will be straightened,
deepened, contoured and paved, which should reduce friction
and speed the flow of drainage down the canal.
The canal will also be nearly 1 ft. deeper.
"We're digging out the bottom, contouring the slopes,
then placing a layer of bedding material on the bottom and
some earthen fill on the slopes," O'Brien added. The
canal bottom is 10 ft. wide and the canal top is 45 ft. wide.
A 12-in.-deep layer of bedding material on the canal's bottom
consists of gravel and pure sand and a 6-in. layer of slope
fill consists of "a finer sand and a smaller stone,"
all supplied by TXI of Baton Rouge.
"The finer sand compacts better, which is critical on
the steep slopes," Lua said.
PVC drain pipe runs lengthwise through the canal bottom fill
material and "branches out every 25 ft., goes up the
slope 6 in. and out the concrete wall" to provide hydrostatic
relief.
Fabric is placed on top of the bedding and the protective
layer of gunite is distributed.
"We then place a single mat of reinforcing steel followed
by 6 in. of concrete for the bottom and the slopes,"
Lua said. The 4,000 psi concrete was pumped up until early
March and had a 5-in. slump.
"We could go to a higher slump, depending on what we
decide to do."
During the concrete pours, crews form and pour the bottom
slab, then use the slab as the bottom support for the slope
concrete.
"Then we just start placing concrete at the bottom and
work our way up the slope. Everything just ties into the canal
bottom," he said. A 30 ft. trailer-mounted screed is
wenched up the slope as the concrete is placed.
"As the screed turns it pushes the concrete up and finishes
it," Lua said. "It has to be screeded several times."
Throughout the process, a sheet pile dam is constructed at
500-ft. intervals and two 6-in. pumps redirect stormwater
around the work area to the other side.
Other work at the site required the extension of corrugated
metal cross drains at several locations along the canal to
connect to the city's existing drainage system, and the demolition
of "a couple hundred feet" of existing paved canal
areas.
Also, a 60-ft. downstream section of the canal is being lined
with a 2.5-ft.-deep layer of 300-pound limestone riprap supplied
by Diversified Materials of New Iberia.
O'Brien said the canal paving project will likely provide
more obstacles for the contractor before it's completed in
fall 2005, but the reward will be an "aesthetically pleasing
design" in a high-visibility area of Opelousas.
"A lot of contractors didn't bid this job because of
the difficult slope," he said. "But in the end I
think it will be a rewarding experience."
Useful Resource:
For more project detail, go to: http://www.la.nrcs.usda.gov/
|