|
Order in the court
Jefferson Parish judges to
get more functional building
By Sam Barnes
Judges for Gretna's Second Parish Court will no longer have
to use public restrooms and maneuver through public waiting
areas once a new $7 million court building is completed in
October.
The court currently shares facilities with other government
agencies in the Jefferson Parish Government complex, which
puts the judges in some awkward situations.
Mike Carbo, site superintendent with general contractor
Woodrow Wilson Construction Co. Inc. of Baton Rouge, said
the new, 67,155-sq.-ft., three-floor court building will include
three similarly-sized courtrooms with private access from
the judges' chambers.
The building, situated across the Mississippi River from
New Orleans, will also have enhanced security measures.
"We're only 'building out' two of the floors, with
the third floor remaining a shell until it's needed,"
Carbo said. The building is made of heavy-gauge steel and
enhanced electrical and mechanical systems to accommodate
future additional floors.
Carubba Engineering Inc. of Metairie and Rozas-Ward AIA Architects
of New Orleans designed the building.
"Design-wise, the detail framing in the courtrooms
will be impressive," said Roy Carubba, owner of Carubba
Engineering. "There are barrel vault ceilings and the
rear walls behind the judges' benches are canted."
Carubba said the millwork provides another aesthetic feature
in the 150-person courtrooms.
"All of the millwork must be sequenced, meaning at
every elevation the grain must be vertically and horizontally
continuous," he added. "The staining of the wood
must also be uniform."
A high-tech audio-visual system will be installed in the
courtroom as part of a separate contract late in the project
and will include projectors, dropdown screens, computer controls
and laptop portals.
"The controls will be located in the court reporter's
area within the courtrooms, but the judges and attorneys will
have the opportunity to plug into the system to run presentations,"
Carbo said.
Tile is used extensively elsewhere in the building, predominantly
in the building's two-story entranceway atrium.
"The abundance of tile in the 27-ft.-tall atrium walls
will create a striking feature in the entrance," Carbo
said. "We're also placing tile on the floors and grand
stair case." Carr Stone & Tile Inc. of New Orleans
is supplying the tile, which was manufactured in Europe and
the United States.
"They're using 12- by 24-in. tile for the walls and
the floor tile has distinctive aesthetic patterns," he
added. Other lobby work requires some decorative crown molding
around the transaction counters.
When work began in May 2003, demolition of an existing parish
building had been completed and the site cleared as part of
an earlier contract.
"The site was actually at grade so we were able to pour
directly on top of that," said project manager David
Broussard. "We drove piles flush with the existing grade,
which was at the bottom of the building's grade beams and
pile caps."
Boh Bros. Construction Co. LLC of New Orleans drove 800 composite
piles made up of 60-ft.-long timber piles and 10-ft.-long
concrete-filled metal cans.
Due to the site's proximity to the Mississippi River, the
contractor needed approval from the U. S. Army Corps of Engineers
before driving piles.
"The corps checked the river stages before issuing
a permit," Broussard said. "If approaching 15 ft.
of flood stage we would have had to stop, but that never happened."
After the foundation was in place, Metropolitan Erection
LLC of Kenner began erecting heavy-gauge structural steel
supplied by Superior Steel Inc. of Baton Rouge.
"We started pouring concrete in November for the 5-in.-thick
elevated slabs," Broussard said. The 3,000-psi concrete
is reinforced with wire fabric.
A significant amount of electrical conduit had to be installed
in the slabs because much of the ceiling space is occupied
by more than 2,500 ft. of mechanical ductwork.
"Since the mechanical room is located at the point
of entry into the building a lot of duct is necessary to service
the building," Carbo said. Atlas Blowpipe & Sheet
Metal Works of Metairie installed the duct.
Putting more electrical conduit into the slab meant more
"layout-intensive" concrete pours.
"Ferguson's Electric of New Orleans had to identify
the location of every wall prior to doing rough-ins,"
Carbo said.
Mechanical components of the building will connect to an
existing central plant about 700 ft. away. Five new air-handling
units will help transport the air.
Exterior construction is highlighted by a large curtainwall
system on the two sides of the building with views of the
Mississippi River.
"The river-view sides have a three-coat cement-based
stucco system and a substantial glass curtainwall system installed
by Orleans Glass," Carbo said. The more expensive 1.5-in.-thick
cement stucco is "a little stronger and a little more
secure" than synthetic stucco, he added.
The remaining two sides are made of painted concrete block
installed by AA Masonry of New Orleans. About 28,000 CMU blocks
are necessary for the walls and two 12-man holding cells inside
the building.
Other work includes the construction of four elevators shafts
for four public elevators, a prisoner elevator and a judicial
elevator. There will be a small private parking area under
the first floor with about 12 parking spaces for the judges
and administrative staff.
Once completed, the building will also have administrative
offices, judges' chambers, Clerk of Court offices and both
criminal and civil contempt of court offices.
"There will be bulletproof glass and metal detectors,
as well as central commands in two locations," Carbo
said. "These will all be tied to Jefferson Parish Central
Command about two blocks away."
Useful Source:
For more information about the Second Parish Court, go to:
http://www.jpclerkofcourt.us/2ndparish_court/Main.asp
|