|
Mississippi River sediment will restore
wetlands just below Venice
Great Lakes Dredge & Dock Co., Oak Brook, Ill., has been
awarded a contract to begin a precedent-setting project to
restore south Louisiana wetlands through the diversion of
Mississippi River sediment and water.
Under the $3.6 million contract awarded in August, Great
Lakes' dredge California will cut through the river's low,
narrow bank six miles below Venice. This would send sediment
and water into West Bay at 20,000 cu. ft. per second.
The U.S. Army Corps of Engineers and the Louisiana Department
of Natural
Resources will share the cost 85 percent federal and 15 percent
local. Construction began in September.
It is the first phase of the $22.3 million West Bay Sediment
Diversion Project to restore 10,000 acres of wetlands over
20 years.
The project is the first to restore coastal Louisiana through
the large-scale diversion of sediments and fresh water directly
from the Mississippi River into coastal marshes. No structure
or gates will be built to operate the diversion.
"This project will harness the natural land-building
power of the river and mimic the natural processes that formed
coastal Louisiana," said Gregory Miller, the Corps' project
manager. "Once this area was coastal wetland, but now
it is shallow, open water."
An interim channel will be dug first, designed to limit flow
to 20,000 cu. ft. per second (cfs) at average river stage.
If experience proves it feasible, the channel would be enlarged
to discharge 50,000 cfs into West Bay.
The interim diversion will be closely monitored before the
larger channel is cut. A relatively small portion of riverbank
and adjacent wetlands will be excavated to build the diversion
channel. The project will be built under the federal Coastal
Wetlands, Planning, Protection and Restoration Act, also known
as the Breaux Act.
Project will help water circulation
in Atchafalaya Basin
The U.S. Army Corps of Engineers has designed a water-management
project to provide water circulation improvements and sediment
management in south Louisiana's great Atchafalaya Basin river
swamp.
The purpose of the Buffalo Cove Water Management Unit is
to enhance fish and wildlife resources. It would benefit more
than 7,500 acres initially and 53,000 to 58,000 acres eventually.
It is located in the lower basin in Iberia, St. Martin and
St. Mary parishes.
A 75-page draft environmental assessment is now available
from the Corps of Engineers. Also available is a draft "finding
of no significant impact" or FONSI, which if adopted
would give the environmental green light for construction.
The U.S. Army Corps of Engineers plans to begin construction
in 2004 on Buffalo Cove, the first water management unit in
the Atchafalaya Basin Floodway System project.
The Buffalo Cove project proposes "to improve interior
circulation within the swamp, remove barriers to north-south
flow, provide input of oxygenated, low temperature river water,
and prevent or manage sediment input into the interior swamps,"
said Larry Hartzog, a Corps freshwater biologist.
DOTD recaps previous fiscal year spending
The Louisiana Dept. of Transportation and Development let
to contract 318 construction projects totaling approximately
$534 million during the fiscal year that ended June 30, according
to DOTD Secretary Kam Movassaghi.
The dollar value represents a $12 million increase over
last year's construction contract lettings and continues a
10-year trend of increased productivity with fewer employees.
"Since 1992," Movassaghi said, "we increased
our average annual construction project lettings by 78 percent,
but lost 250 employees during that same time.
"Doing more with less is not new for DOTD," he
said. "Although the Louisiana Transportation Trust Fund
created in 1989 provides a dedicated source of revenue, the
fuel tax has never been adjusted for inflation or rising construction
costs. Since 1989, the buying value of a dollar has decreased
to about 60 cents, so doing more with less is an annual challenge
for us."
Compared to past average lettings of $50 million per year,
DOTD issued $172 million of TIMED project lettings under its
accelerated construction plan.
"Our targeted spending on the TIMED program this year
was $162 million," Movassaghi said. "We actually
let 20 TIMED construction projects valued at $172 million.
Additionally, we completed seven TIMED project segments, two
clearing and grubbing contracts and 29 miles of brand new
highway."
|