|
Delays, disruptions and damages:
A brief overview of construction litigation
By Randy Bonnecaze
A construction project brings together many different parties
and involves an intricate sequence of interdependent transactions
and events. Any delays or changes can inhibit a contractor
from meeting his or her contractual obligations.
Should such a problem arise on your next job, you need to
understand the costs you may be able to recover as well as
how damages and profit losses are calculated.
Delays affecting job progress.
Project slowdowns are common. Excusable delays may
result from unforeseeable events (such as severe weather or
civil unrest) that are beyond the owner's control. But delays
become compensable when an owner's (or other party's) actions
or inactions delay your work. Typical compensable delays include:
In preparing for these slowdowns, carefully review your contracts
and reject overly broad "no damages for delay" clauses.
Doing so is important because, absent these clauses, a compensable
delay may entitle you to a time extension and a damage reimbursement.
Generally, you may recover one of four cost types for a compensable
delay claim:
1. Extra work expenses.
To claim costs for extra work, you must first delineate
the additional labor's extent. Then you need to prove that
previous change orders in the contract didn't include the
extra work. Last, you must calculate the added labor, materials
and other costs as well as the change's effect on profitability.
2. Extended contract performance
costs. If you're using rented equipment and the owner
(or another party) delays a project, you're usually entitled
to reimbursement of the equipment's rental cost for the
additional days. So retain all rental documents for each
job, because you'll need these to file a claim.
3. Increased unit prices.
To win a delay claim citing increased unit prices, you must
prove that the costs you incurred in later job periods had
higher unit prices than those that would have existed had
no delay occurred. Because most projects call for various
skilled trades at a range of different wage levels, labor
costs are the most commonly reimbursed unit prices.
4. Project acceleration
expenses. Sometimes an owner may accelerate a job
while refusing to allow you a proper time extension. In
turn, you must revise the job schedule to complete the remaining
activities in less time than you would have needed absent
the acceleration. When this happens, you may receive compensation
for additional costs such as increased manpower and overtime,
as long as you can substantiate their occurrence.
Disruption of projects.
An owner might disrupt your work force because of late delivery
of owner-supplied equipment or materials, excessive field
inspections, or delayed site access. In some cases, you may
recoup these expenses by filing a claim. The four main ways
of calculating disruption damages are:
1. The measured mile method.
Here an analyst (typically a CPA or similar professional)
compares the disrupted work's cost with the expense of similar
work performed without disruption. This method's advantage
is that it uses the productivity rates actually achieved
on the project in question.
2. The industry standard/personal
experience method. In this case, an analyst uses
either industry productivity standards or your personal
experience from other projects to determine damages. The
analyst then must adjust the productivity measure for factors
unique to the project at hand. These adjustments are often
difficult to quantify, making this method less desirable
than the measured mile method.
3. Engineering analysis.
Sometimes the analyst may draw on research studies that
analyze two similar projects and review the effects of delays
and disruptions on one project to a comparable job without
interruptions. He or she applies data from these studies
to the disrupted job, fine-tuning his or her calculation
to account for that project's specifics. Again, the disadvantage
is that these subsequent adjustments may not directly correlate
with the data taken from the studies.
4. The total cost method.
Because it's overly broad, this is generally the least preferable
option. With the total cost method, the analyst calculates
recoverable damages by subtracting the bid costs plus profit
from the total actual costs including profit. To be successful,
you must prove that you deserve a recovery and any other
calculation method would be impractical.
Damages to profits. In
addition to recovering unforeseen costs, you may recoup the
lost profits that you would have earned had you completed
the project. But, in any claim, you retain the responsibility
to act as necessary to overcome the breach of contract's ill
effects. For example, if you lose an income-producing asset,
such as a bulldozer, you cannot recover lost profits the asset
would have produced beyond the reasonable period you should
have taken to replace it.
Thus, generally, the amount of earnings you lose because
of your own failure to mitigate damages isn't recoverable.
But you can typically recover lost profits any time you're
unable to complete a project, or a job is inexcusably delayed,
because an owner (or other party) breaches the contract. Three
main methods of calculating such damages exist:
1. The before-and-after
method. Here an analyst compares revenues before
the alleged contract breach with revenues after the breach.
Assuming your operations before and after the event in question
are comparable, you may contend the breach caused any reduced
revenues.
2. The yardstick method.
In this case, the analyst compares your earnings with those
of a similar business, product or other measure. The best
yardstick for a closely held construction business is another
builder of similar size and specialty in the same area.
3. The "but for"
method. This involves projecting your company's operations
absent (or "but for") the alleged effects of the
other contract party's actions. To determine the amount
of lost profits, the analyst compares the profit suggested
by the projection with the actual profit you realized.
Protection measures. Please
note that laws vary by state. So you should consult your attorney
for specifics about your situation.
Editor's Note: Randy
J. Bonnecaze is a Certified Public Accountant (CPA) with Hannis
T. Bourgeois LLP, Baton Rouge.
|