LSU Tiger Stadium
(East Side Expansion)
Contractor: MAPP-BEERS (A Joint Venture), Baton Rouge
Location: Baton Rouge
Cost: $40 million
Project managers: Jim Doucette & Vernon Anderson
Jobsite superintendent: Roy Aiklen
Architect: Trahan Architects, Baton Rouge
Upon completion of its 11,000-seat addition last summer,
LSU's 75-year-old Tiger Stadium became one of the largest
on-campus football stadiums in the country, made possible
by a unique financial arrangement through the Tiger Athletic
Foundation.
"This is an exciting and important step for LSU Athletics,"
said LSU Athletic Director Joe Dean. "Tiger Stadium has
long been one of the great arenas in the world of athletics,
and this expansion (has reinforced) that status well into
the next century."
The expansion gives Tiger Stadium approximately 90,665 seats,
making it the fourth-largest on-campus collegiate football
stadium in the country behind Tennessee's Neyland Stadium
(102,544), Michigan Stadium (102,501) and Penn State's Beaver
Stadium (93,967).
According to joint venture project manager Vernon Anderson,
MAPP-BEERS, Baton Rouge, the high-rise structure is 13 stories
of cast-in-place concrete, with precast hollow core plank
and concrete slab construction. It has three passenger elevators
and one freight traction type elevator, as well as four switchback
escalators.
The mechanical system is a chilled water supply piped system
with air handler units at the mechanical mezzanine level,
and is equipped with a booster firewater pump, domestic water
pump and emergency generator system.
Anderson said the design/build project is unique in several
ways. First, the project's design and construction were driven
by a fast-track accelerated construction schedule, with only
625 days from start to completion.
Second, the unique nature of operating in an active university
campus, with daily and seasonal activities, required special
attention by the construction team, i. e. test days, which
required no noise, and game days, which required special security
and setup activities to protect the construction site and
visiting fans.
MAPP-BEERS had to make special provisions for the safety
of the public/fans, visiting team, equipment vehicles and
buses, and protection of the construction site during the
seven home games. These provisions included fencing, temporary
concrete walks and drives, and cleaning and washing down the
areas where the fans and visiting team entered the existing
stadium.
Since these areas were located in the middle of the construction
site, construction activities were halted from mid Friday
afternoon until Sunday morning.
Thirdly, there were tight site requirements. The actual construction
site was located between the existing stadium and surrounding
dormitories. In fact, construction at the existing stadium
was within 10 ft. of the existing dormitories.
One of the biggest challenges came at the project's outset,
when crews had to work around existing underground utilities
that were more than 75 years old and 100-year-old oak and
magnolia tress that could not be removed.
"Every day, we encountered utilities that the university
did not know existed," Anderson said. "We worked
closely with the University Facilities Department and the
architect and engineer to locate, isolate and either relocate
or update these utilities. The fact that these utilities were
there and no one knew about them impacted our construction
schedule by approximately four to six weeks."
|