|
New Worship Center & Education
Wing, West Monroe First Baptist Church
Contractor: Lincoln Builders Inc., Ruston
Location: West Monroe
Cost: $12 million
Project manager: Nat Mixon
Jobsite superintendent: Junot Dixon
Architect: Fuqua Osborn Architects, Huntsville, Ala.
A variety of complexities in the design and construction
of a new 2,750-person worship center in West Monroe tested
the limits of scheduling and designer-contractor communication.
The West Monroe First Baptist Church Worship Center, built
at the church's existing complex as part of an $11 million
project, was first and foremost a complex steel project, requiring
the placement of a variety of difficult steel truss spans
for the building's high pitched roof.
Dramatic lifts accentuated this complexity, as Monroe's Ranger
Erectors assembled and lifted two heavy-steel trusses spanning
80 ft. long and 10 ft. tall, and weighing approximately 37,000
pounds apiece.
Junot Dixon, jobsite superintendent with general contractor
Lincoln Builders Inc., Ruston, said each of the trusses arrived
at the site by truck in three pieces (after being fabricated
by Steel Fabricators of Monroe), then were welded together
at the site with plates about 1 in. thick.
"It took us about three days to weld one truss up, using
two cranes to set them," Ranger Erectors' Randy Wygal,
owner, explained. "From there, we went up with the pitched
roof, which is a steel frame structure including 'jack-rafters,'
ridges and bar joists."
During the lifts, Wygal said, Ranger Erectors placed a lattice
boom crane in the middle of the building site since nearby
power lines and existing buildings would have made it difficult
to lift and place the beams from another location.
As a whole, the steel erection for the worship center had
to be scheduled in 11 sequences, which allowed sections of
the steel to be installed prior to the completion of designs
for the entire building.
"If we had waited for the whole job to be designed,
we wouldn't have been able to 'dry in' the building when we
needed to. The roof installation was our most 'critical path'
item - prior to its completion none of the interior crafts
could begin their work on the worship center," Dixon
said.
The roof covering, itself, is also complex, incorporating
a composite roof deck that consists of a metal deck layered
with insulation, plywood and gypsum board. The complex, and
expensive, roof provides a "fire-rated" system.
"The initial costs of the roof 'weigh out' over time,"
Dixon said. Once all its components are in place, the roof
will measure up to 2.5 in. thick.
|