|
Enterprise Fractionation Plant, ISBL
Expansion Project, Norco
| Owner:
Enterprise Products Operating LP, Norco
Contractor: Performance
Contractors Inc., Baton Rouge
Cost: $8 million
Engineer: URS Corp.,
New Orleans
|
Enterprise Products' ISBL expansion project was a complex
project combining various types of industrial construction
under a lump sum contract. The expansion project included
four major phases: pipeline pumps project, ISBL foundations
project, ISBL mechanical expansion project and the storage
sphere hook-up.
Due to economic conditions and the time required to produce
detailed engineering plans, Enterprise elected to competitively
bid the different phases of construction on a lump sum basis.
Each package was bid separately with consideration to what
cost and schedule impact they would have on the work in progress
and future packages.
In addition, several addendums were issued to each package
as detailed engineering was finalized. The profitability of
the project is directly proportional to the volume of natural
gas liquids processed daily. The outcome of the project was
a 40 percent increase in capacity.
The project generated some unique circumstances and challenges
to the owner, engineer and contractor. The project consisted
of the major revampment of the existing fractionation facility
with a 21-day critical plant shutdown that included capital
project work and integrated maintenance activities.
Seventy-two percent of the work was performed in an operating
unit of the fractionation plant over an 11-month duration.
The remaining 28 percent was completed during a shutdown of
the unit for a 21-day "around the clock" unit turnaround.
Maintaining the logically tied detailed schedule and tracking
systems enabled the project team to make sound decisions with
regard to areas of priority and workweek schedules. The overall
project plan included the activities of all subcontractors,
as well as owner inspection hold points and milestone delivery
dates.
|